Battersea Power Station
You are here:

PROJECT: Battersea Power Station Enabling Works
LOCATION: Battersea Power Station, London
CLIENT: Parkview International
VALUE: £1,000,000
PROJECT OVERVIEW: CMP were contracted to construct 4 Berthing Dolphins alongside the new development at Battersea Power Station. Refurbishment of the existing concrete jetty works included removal of redundant fenders and screens, and installation of new fender system.

WORKS DESCRIPTION:

  • Construction of 4 Nr dolphins consisting of 2 raked piles and 1 vertical pile
  • Fabrication of steel pile link framework
  • Dredging arisings from around the jetty
  • Removal and dismantling of pipe carrier system
  • Remove existing timber fenders and replace with new
  • Dismantle and remove walkways from below the jetty structure

PROJECT IMAGES - To open an image in a new window please click on it.

Description:

Number of Pictures:  of