PROJECT: Brentford Island LOCATION: Brentford, Middlesex CLIENT: Taylor Woodrow Management VALUE: £810,000 PROJECT OVERVIEW: CMP were contracted to undertake various dock and river repairs as part of a prestigious new housing complex.
WORKS DESCRIPTION:
Install 92 linear metres of sheet piles along the existing riverbanks
Install 92 metres of concrete capping beam measuring 700 x 600mm upon the sheet piles
Install timber facing to sheet piled sections
Place 75 metres of gabion mattressing with coconut growth matting along the river banks
Refurbish the existing dock and river walls including re-building sections and re-pointing
Refurbish historic weir
Install a cofferdam to enable the coring of a 250mm diameter drainage outfall in the dock walls under the water level
Works undertaken from both pontoons and from the dockside