PROJECT: Canary Wharf Access Bridge/Deck LOCATION: Canary Wharf, London CLIENT: McNicholas Plc VALUE: £450,000 PROJECT OVERVIEW: CMP were contracted to install a watertight Cofferdam to enable the construction of a hydraulic ram pit to activate a new lift bridge.
WORKS DESCRIPTION:
Temporary access deck designed and installed to allow access over Canary Wharf dock
Watertight Cofferdam with five framing levels installed using 22m sheet piles
Cofferdam excavated to 12m depth
All works subsequently extracted