Crowdy Resevoir
You are here:

PROJECT: Crowdy Resevoir Aeration System
LOCATION: Crowdy Resevoir, Devon
CLIENT: South West Water
VALUE: £70,000
PROJECT OVERVIEW: CMP were contracted to install a 500m aeration pipe within the reservoir to prevent water stagnation.

WORKS DESCRIPTION:

  • Oversee manufacture of specially designed aeration pipe
  • Weld MDPE pipe into 500m length
  • Attach ballast weights to pipe
  • Attach buoyancy and tow into position
  • Remove buoyancy and carefully sink pipe onto the reservoir bed