PROJECT: Harefield Cofferdams LOCATION: Harefield, Greater London CLIENT: Murphy Group for National Grid VALUE: £1,800,000 PROJECT OVERVIEW: CMP were contracted to install and extract approximately 20nr cofferdams to enable the laying of a new high pressure gas main between Harefield and Southall, North/West London
WORKS DESCRIPTION:
Drive and extract cofferdams in approximately 20nr locations
Supply and Install frames within cofferdams up to 12m deep
Works locations generally surrounded by existing properties so there was very careful attention to detail by the client with regards to working methods, interaction with the general public and general presentation of the company
Project required extensive plant movements in and around residential areas
PROJECT IMAGES - To open an image in a new window please click on it.