PROJECT: Holyhead Footbridge River Crossing LOCATION: Holyhead, Isle of Anglesey CLIENT: Laing O'Rourke VALUE: £800,000 PROJECT OVERVIEW: CMP were contracted to install rock-socketed piles to support Holyhead footbridge.
WORKS DESCRIPTION:
Phase 1 -
Mobilise and position the General Zee jack-up barge
Drive casing tubes into rock from jack-up barge
Drill socket through casing tubes and clean out debris
Install steel reinforcement structures within casing tubes
Fill casing with concrete
Install pre-cast concrete crossheads on top of piles
Place and install pre-cast concrete decking beams
Phase 2 -
Continuation of rock-socketed foundation piling works from phase 1 but completed from the shore rather than the jack-up barge