M25 Widening
You are here:

PROJECT: M25 Widening
LOCATION: London, England
CLIENT: Skanska Balfour Beatty JV
VALUE: £1,400,000
PROJECT OVERVIEW: CMP were contracted to install sheet piling on the M25 widening between Junctions 16-18

WORKS DESCRIPTION:

  • Joint venture formed with Kim Barker to allow mobilization of up to 7 piling gangs installing sheet piles with leader rigs, excavator mounted rigs, conventional rigs and silent and vibration-free techniques
  • Majority of installation completed with telescopic leader rigs (TLR) drop hammer used for final driving where required
  • Unique King Sheet Pile (KSP) Retaining Wall System utilised to save a minimum of 33% of the mass of steel when compared to a conventional sheet piled wall
  • Achieved an average of 1,000-1,100m2 sheet pile installation per week or 20 to 25m run of piling per day
  • Production reached a high of 1370m2 installation, 120 pairs of piles between 9 and 11m, in one week
  • A total of 22,000m2 of steel piling driven throughout project

PROJECT IMAGES - To open an image in a new window please click on it.

Description:

Number of Pictures:  of